You are currently browsing the Relish & Wasabi Get A Home blog archives for August, 2011


Day 177

Move in! Ok, we’re not quite ready for that housewarming party and still have a few pieces to finish up but internet is setup and computers are moved over so we are officially operational! Monday will be day 1 of life at 205.

nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image

Day 174

Two days left! A/C installed, phone/network connections finished, lighting, exit signs, stair railings, and a few other remaining items for inspection.

nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image

Day 173

Ok, maybe a few more tasks before the cleanup starts…

nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image

Day 168 – part 2

A bit of tiling, a bit of plumbing, a bit of electrical, and we’re ready for furniture.

nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image

Day 168 – part 1

An update so big, it required two posts! We’re really down to the final steps now and with just a week and a half left till move in, the todo list is getting shorter.

nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image nivo slider image

Day 160

Still plenty of finishing touches left but the painting has begun, shelves are going in, and we are inching our way to the finish line.