Move in! Ok, we’re not quite ready for that housewarming party and still have a few pieces to finish up but internet is setup and computers are moved over so we are officially operational! Monday will be day 1 of life at 205.
Day 174
Two days left! A/C installed, phone/network connections finished, lighting, exit signs, stair railings, and a few other remaining items for inspection.
Day 168 – part 2
A bit of tiling, a bit of plumbing, a bit of electrical, and we’re ready for furniture.
Day 168 – part 1
An update so big, it required two posts! We’re really down to the final steps now and with just a week and a half left till move in, the todo list is getting shorter.
Day 160
Still plenty of finishing touches left but the painting has begun, shelves are going in, and we are inching our way to the finish line.